Capital Improvement Project
This timeline represents our current goals and proposed schedule. As with any large-scale, multi-year project, dates are subject to change based on construction progress and other factors. We'll be sure to keep the community updated along the way!
-
These improvements will help us respond to the changing needs of our families. To put it simply, we need more space to provide vital services. This isn't based on future projections; these are real-time needs in our buildings, today.
Currently we have to offer "Art on a Cart" in some classes; essential AIS (Academic Intervention Services) in hallways; and have Special Education students change schools to go where a program is offered, to name just a few challenges.
How will we find space? We'll add on to our junior high schools and move 6th grade there. This allows more room at the elementary level, so we can increase services and allow our 6th graders to have a true middle-school experience: more electives, tech classes, and high-school courses.
This project includes so much more: essential improvements to our secondary-school athletic facilities, and many other structural upgrades and repairs district-wide.
-
-
Add 37 total middle-school classrooms: Offer more exploratory classes and electives to 6th graders
-
Free up 33 total elementary-school classrooms for services like AIS, as well as art classes, band lessons, and more
-
Allow Special Education students to stay in their home school, by opening up more classes in our buildings
-
Reduce the need to send students out of district for programs
-
Offer support for our English Language Learners
-
Upgrade athletic facilities at secondary schools: new turf fields and more access for community teams
-
Building improvements district-wide: repairs and upgrades
-
-
Construction Cost $126,032,400 Incidental Costs* $27,735,600 Total $153,768,000 *May include hazardous materials testing, geotechnical testing, site surveys, storm water pollution protection design, special inspections testing, construction insurance, furniture & equipment, design fees, legal fees, construction management, etc.
Estimated timeline for when costs will impact your tax bill:
School Year 2024-2025 | 2025-26
No Impact on TaxpayerSchool Years 2026-27 | 2027-2028 | 2028-29 | 2029-30
We begin work, using short-term, interest-only loans to pay contractors along the way.-
The District only pays interest on this type of loan, and it’s included in the annual school budget until the project is complete.
School Year 2030-31
We anticipate completing the project, and consolidating all debt into a long-term loan.-
Once the project is complete and permanent financing is in place, a homeowner with an assessed value of $400,000 would pay approximately $25 a month.
-
We are also anticipating about $67,300,000 in State Aid.
-
-
This multi-year, long term project will be done in phases, so it will be a few years: we're estimating it will take place in the 2030-31 school year. Work on the additions will begin in the summer of 2027.
Site Improvements
-
- New artificial turf soccer/softball field, portable bleachers, lights
- Press box/concession stand renovations
- Additional parking below baseball field
- Reconstruction of walkway from feature field
- Potential additional road to Patriot Way
-
- New artificial turf soccer/softball field with portable bleachers and lights
- Eight new tennis courts
- New fencing at softball field
-
Addition of 23, 650 sq ft includes:
- 16 new classrooms
- Expanded cafeteria
Other Improvements
- Reconstruct fields for proper drainage
- New basketball court
- Athletic field lighting
- New press box/concession stand; portable bleachers
- Walking track
- Reconstruct back drive loop; improve drop-off parking
-
Addition of 33, 820 sq ft includes:
- Two dedicated music rooms
- Cafeteria relocated to the first floor
- Small-group room
- Small gym
- 18 more classrooms
Other Improvements
- Add athletic field lighting
- New press box/concession stand and portable bleachers
- Replace deteriorated entrance steps
-
Brinckerhoff ES
- Reconstruct driveway & parking lots
- Reconstruct sidewalks
Fishkill ES
- Reconstruct driveway & parking lots
- Reconstruct sidewalks
- Add exterior lighting
Gayhead ES
- Upgrade site lighting
Myers Corners ES
- Site feasibility study to investigate improved vehicle access to site and additional parking.
- Digital display sign at site entry
Sheafe Road ES
- Reconstruct basketball court
- Upgrade ramps to comply with ADA
Building Improvements: Secondary Schools
-
- Re-point original brick
- Replace old ceilings
- Replace original electrical panels
- Upgrade PA system
- Renovate technology classrooms
- Renovate large group instruction room
- Increase electrical service to building
- Modify toilet rooms for handicap accessibility
-
- Re-point original brick
- Replace science wing roof
- Replace old ceilings
- Modify toilet rooms for handicap accessibility
- Replace original electrical panels & upgrade PA
- Renovate technology classrooms
- Renovate large group instruction room
- Handicap ramp at gymnasium entrance
-
- Re-point original brick
- Replace old ceilings
- Modify toilet rooms for accessibility
- Replace original electrical panels
- Add cooling to auditorium and gymnasium
- Replace steam piping in tunnels, unit ventilators and add exhaust fans in classrooms
- Replace asbestos tile at selected classroom floors
-
- Re-point original brick
- Replace roof
- Add cooling to auditorium and gymnasium
- Replace old ceilings
- Replace original electrical panels and exist signs
- Modify health suite and toilet rooms for accessibility
- Re-finish selected classroom wood floors
Building Improvements: Elementary Schools
-
- Re-point original brick
- Replace old ceilings
- Modify toilet rooms for accessibility
- Replace original electrical panels & upgrade PA
-
- Re-point original brick
- Remove remaining asbestos tile flooring
- Replace rooftop units
- Upgrade PA system
- Install main switchgear
- Modify toilet rooms for accessibility
-
- Replace selected original electrical panels
- Renovate four toilet rooms for accessibility
-
- Re-point original brick
- Replace old ceilings
- Add exhaust ventilation, replace rooftop units
- Modify toilet rooms for accessibility
-
- Re-point original brick
- Replace old ceilings
- Replace old electrical panels
- Replace fire alarm system
- Modify toilet rooms for accessibility
- Upgrade PA system
-
- Replace primary feed
- Re-point original brick
- Replace old ceilings
- Replace roof & skylights
- Replace air handlers
- Upgrade cafeteria/gym ventilation
- Replace fire alarm system
- Add elevator
- Modify toilet rooms for accessibility
-
- Re-point original brick
- Replace roof
- Replace remaining ceilings
- Replace fire alarm system
- Modify toilet rooms for accessibility
-
- Replace roof
- Replace exhaust fans, unit ventilators and rooftop units
- Replace fire alarm systems
- Modify toilet rooms for handicap accessibility
-
- Re-point original brick
- Replace corridor ceilings
- Replace fire alarm system
- Modify toilet rooms for accessibility
- Add exhaust fans to classrooms, replace rooftop units